Project Status

Construction: Not started, Design: Completed

Project Overview

This project will provide passive and active recreational opportunities for the communities in the Lealman Community Redevelopment Area (LCRA). The planned amenities include a playground and challenge course, a multi-purpose playfield, dog parks, picnic shelters, restrooms, parking areas and a park maintenance building. A trail is planned to connect the entire park and proposed facilities.

Project Timeline

  • Design: January 2019 – Fall 2023
  • Contract Award: April 2024
  • Construction: Summer 2024 – Winter 2026

Park Improvement History

  • 2004: Lealman Recreation Survey conducted
  • 2005: Joe’s Creek Greenway Park dedicated and Phase 1 completed
  • 2008: Phase 2 completed
  • 2011: Phase 3 completed
  • 2013: Phase 4 completed
  • 2017: Public engagement for Joe’s Creek Greenway Park

Community Outreach

Project Information Meeting
May 23, 2019, 5:30 – 7:30 p.m.; Lealman Exchange, 5175 45th St N., St. Petersburg

Project Funding

This project is supported by:

  • The Penny for Pinellas
  • Federal award number SLFRP4653 awarded to Pinellas County Government by the U.S. Department of the Treasury
  • A Land and Water Conservation Fund (LWCF) Program grant through the Florida Dept. of Environmental Protection

Contact Us

Dan Glaser, P.E.
Project Manager
Public Works / Capital Improvements
14 S. Fort Harrison Ave., Clearwater, FL 33756
(727) 464-5209
dglaser@pinellas.gov